Location: Torino - Lingotto Area ex-railway yard.
Sole Contractor: Mr. Franco Pavan, engineer
Designers: HOK Sport Ltd, Studio Zoppini Associati
Structures: Buro Happold Ltd, MSC Associati s.r.l. - Costruzioni CIMOLAI Armando s.p.a.
Safety: Mr. Pietro Rousset, engineer
Equipment: Buro Happold Ltd, eng. Eugenio Roncelli, eng. Giovanni Consonni, eng.
Geological survey: Studio Cancelli Associato
Environmental feasibility: Pietro Cordara, architect
Civil Engineering: Studio Corona, Teksystem Studio Associato, Prodim s.r.l.
Cost of work: 62.17 million euros
Co-financed by the City of Torino: 7 million euros
Work: In progress, begun 07/05/2003
Expected delivery: Spring 2005